A stretch of dunes in Townsends Inlet is sheared away, leaving steep mini-cliffs nearly 15 feet high.
By DONALD WITTKOWSKI
Sea Isle City’s beaches and dunes suffered “major” damage in some areas during the stalled coastal storm that pounded the Jersey Shore in the first week of October, according to a newly released state report.
The New Jersey Department of Environmental Protection conducted a detailed survey and damage assessment of 81 beachfront sites in Atlantic, Cape May, Cumberland, Monmouth and Ocean counties in the aftermath of the storm.
Of all the sites that were surveyed, 63 had only minor beach or dune erosion. However, six sustained moderate erosion and 12 suffered major damage to the beaches and dunes. Sea Isle was one of the 12 communities having major damage, the report says.
Most of the significant damage in Sea Isle was concentrated on the beaches and dunes near John F. Kennedy Boulevard in the center of town and in the Townsends Inlet section of the island south of 84th Street.
In some spots, the waves washed up to the upper portions of Sea Isle’s beaches and dunes during high tide. The ocean actually penetrated into the dunes in some areas, according to the report.
The remnants of Hurricane Ian and a strong nor’easter that lingered along the coast for four days during the first week of October packed a one-two punch that caused significant erosion to Sea Isle’s beaches, pathways and dunes.

Some of the pathways to the beach were left in rough shape.
Sea Isle’s beaches remain open, but there are some pathways that have been blocked off because of the steep drop-offs in the dunes.
The city’s Public Works Department has been using earthmovers to level off some of the damaged beach pathways so that they could be reopened to the public.
Desiderio noted that Sea Isle has already been in contact with the DEP and the U.S. Army Corps of Engineers to address the beach and dune erosion.
“(Sea Isle) will continue to work with them to ensure that our shoreline remains strong,” he said in the statement.
Sea Isle is expected to benefit from good timing for its next beach replenishment project supervised by the Army Corps of Engineers. In 2023, Sea Isle, Strathmere and the south end of Ocean City will be part of an estimated $30 million project to replenish the beaches with new sand. The contract for that project still must be awarded, so it is not yet known when the project will start and be completed.
“All areas that need replenishment will be included in the project; and, at this point, we expect the project to include at least the downtown beaches fronting the Promenade and the beaches in Townsends Inlet south of 80th Street. That being said, definite locations for beach replenishment will not be established until the project is awarded,” city spokeswoman Katherine Custer said Monday in an email.
Regardless of when the replenishment project takes place, beach closures will be limited to only the area where the work is taking place. The same procedure was followed in previous beachfill projects, Custer noted.
“We don’t shut down our entire shoreline at one time – just the areas where work is being performed, thus to limit the impact on the public,” she said.
Heavy construction equipment and big pipes were used in 2020 for the most recent major beach replenishment project in Sea Isle.